2027 Capital Projects Committee, Meeting 2: June 22, 2026


The Capital Projects Committee meeting on June 22 focused on funding requests totaling over $43 million for various infrastructure and engineering improvements, including road maintenance, bridge repairs, and flood management projects.

• Meeting conducted for the Projects Committee on June 22, with all members present.

• Capital overlay program requests include $9 million for road maintenance and $10 million for engineering improvements.

• Highway safety funds replace damaged guide rails and address recognized deficiencies.

• Federal Aid Bridge New York construction funds request totals $11 million for deteriorating bridges.

• Requests include inspections for small bridges and culverts, ensuring safety and prioritizing repairs.

• FEMA funding obtained for North Forest reconstruction project, addressing slope stabilization and drainage improvements.

• Discussed funding requests for various civil engineering and infrastructure projects for 2027.

• Requested $250,000 for on-call general civil survey and geotechnical services.

• Requested $1.2 million for Springville Dam rehabilitation design to ensure compliance and safety.

• Proposed $10.6 million for large culvert replacements due to aging infrastructure.

• Requested $2.5 million for general road design program to address multiple road projects.

• Highlighted ongoing issues with road stability and drainage improvements across several projects.

Action items:

• 0:15:29 Send the new letter requested by a participant.

• 0:30:59 Provide an overall status update on existing federally funded bridge preservation projects.

• 0:33:11 Confirm the details regarding the inspection of flagged bridges and culverts, including examples of red and yellow flags.

• 0:34:30 Check on the status of funds that were not spent in previous years for emergency engineering design services.

• 0:41:45 Follow up on the request for on-call general civil survey and geotechnical services for $250,000.

• 0:43:29 Explore funding options with DEC for the Springville Dam rehabilitation design project.

• 0:49:21 Confirm details regarding the preservation of large culverts and related construction projects for 2027.

• 0:52:34 Continue discussions with DEC commissioners regarding drainage issues affecting farmers and small culverts.

• 1:02:37 Ensure that design funding requests align with future construction timelines for various bridge projects.

• 1:10:05 Assess the feasibility of repairing or reconstructing Dodge Road and New Road, considering alternative solutions like milling and overlay.