Gov. Kathy Hochul told Spectrum News’ Capital Tonight that she has placed a first-in-the-nation pause on new data-center proposals while New York develops rules to protect host communities, require greater community benefits, and prioritize cleaner power sources.
Speaking with host Susan Arbetter, Hochul said the state has seen a flood of proposals — she cited roughly 30 pending applications — and that she needed to “put on the brakes” to make sure communities get a better deal. She said projects that already have permits will continue to move forward.
Hochul described a forthcoming community investment framework that would give municipalities a negotiating “playbook” so small towns with limited economic development staff are not negotiating alone with large companies. She said the framework could include requirements that data centers support local schools’ access to AI technology, contribute toward local infrastructure such as water and sewer upgrades, and provide other community amenities.
On energy, the governor said New York wants data centers to focus on renewable sources or “bring their own power source” and to contribute to costs rather than shifting them to ratepayers. She called for an “all-of-the-above” energy approach in the near term — including repowering older plants to make them cleaner — while continuing to pursue more renewable and nuclear capacity as longer-term solutions.
Hochul also framed the pause as a way to protect New Yorkers and major job-creating investments the state has attracted, pointing to Micron and other manufacturers that rely on affordable Upstate energy. She said the moratorium is intended to ensure that hosting a data center is a “net positive” for local communities rather than a drain on local services and taxpayers.
The governor’s comments were delivered during an interview on Spectrum News’ “Capital Tonight” with Susan Arbetter; an audio version and a rush transcript were provided by the governor’s press office.
Key points from the interview:
- Hochul cited about 30 pending data-center applications and said she paused new approvals to “get it right.”
- Projects that already have authorized permits will proceed.
- The administration will develop a community investment framework to guide local negotiations and require community benefits.
- Hochul emphasized preferring renewables and nuclear power for data centers and said companies should help offset costs so ratepayers don’t shoulder additional expenses.
- She supports short-term measures such as repowering older plants to bridge energy gaps while building longer-term renewable and nuclear capacity.
The governor repeatedly framed the move as protecting residents and ensuring long-term economic benefits for New York communities if they host data centers after the pause ends.
What’s still unclear: the press material does not specify the moratorium’s formal legal mechanism, exact scope or duration, which agencies will implement the framework, or a timeline for when the pause will end. Editors may want to follow up with Empire State Development, NYISO, DEC or the governor’s office for implementation details and any listings of specific affected projects.